Continued Growth in Renewable Energy Projects

August 1, 2006
Richmond, Virginia


RICHMOND - INGENCO's expansion is well-underway, with five new plant projects under development including:

 

Virginia  - Brunswick County and King & Queen County

North Carolina - New Bern

Pennsylvania - Pine Grove

Maryland - Wicomico County

The Brunswick site has been selected, permits issued and the well and septic studies are being reviewed.  At the King & Queen site, INGENCO is awaiting approval of the building permit.

Ground has been cleared, the foundation pad added and the well, septic and wastewater systems engineered for the New Bern project.  The final permit to begin hard construction is expected to be issued in mid-October, with staffing to occur in mid-November.

At the Pine Grove site, pipeline engineering is in progress.

The building permit has been received for Wicomico, the site has been cleared and the building is on location.  Additionally, engineering for the well and septic system has been completed. INGENCO is in the beginning stages of staffing the plant.